Case Study

Construction

Solution
Hussh Pod 30/45
Generator
60kVA
Term
30 Days
£5,847

Fuel Saved

10,290kg

CO2 Reduced

556 hours

Generator Runtime Reduced

Over the month period, the site in Dumfries ran 77% on battery, leaving only 23% on the generator.
Construction

THE CHALLENGE

Our construction client needed to reduce their CO2 emissions and fuel costs by running their site cabin set-up on battery power for as long as possible, without compromising on performance. This consisted of an office, a drying room, a canteen, and a toilet block, in Dumfries, Scotland.

THE SOLUTION

Our team assessed our client’s on-site power demands before recommending an optimised solution that was appropriate for the application. Alongside a 60kVA generator, we proposed our Hussh Pod 30/45 – 45kWh of useable energy storage with 30kVA three-phase inverters.

THE RESULTS

The integration of the Hussh Pod into our client’s power set up reduced generator run time over the hire period by 556 hours, saving the client £5,847 in fuel costs and reducing CO2 emissions by 10,290kg.

Over the month period, the site in Dumfries ran 77% on battery, leaving only 23% on the generator.

As part of the Power Saving Solutions service, reporting is sent to our client to demonstrate performance, savings and return on investment.

Statistics based on a comparison of using a sole traditional 60kVA diesel generator, at a cost of £1.50/L at 7L per hour.