Birmingham – Construction

Case Study

45/90  Erica Board 

 

Site Overview

With the challenge of powering 22x cabins on a large house building development consisting of apartment blocks and houses, they needed a hybrid solution which allows the site to run at night efficiently and quietly. Our team began to assess which
Hussh Pod would be most appropriate application to power 22 cabins, and we decided to utilise 2 of our BESS Hussh Pod 30/45’s alongside 2x Erica boards for distributing power efficiently on-site for a 7 month hire period.

Innovation and Sustainability

This resulted in the Hussh Pods running the site 66% of the duration of the 191 days they were on hire, resulting in a reduction of 6,085 hours in diesel generator run-time. In doing so, our client’s savings on their fuel has resulted in £79,123.92 across the two Hussh Pods with 160,683.42kg of CO2 emission savings.

Our efficient digital engineer and onfield engineer teams have been onhand to assist the site management to efficiently use their Hussh Pods and Erica Boards throughout the duration of the hire.

Our Client Purchased:

2 x Hussh Pod 30/45’s
2 x Erica Boards

Powering:

Cabins on a construction site

6,085L

Fuel Saved*

£79,123.92

Money Saved*

160,683.42kg

CO2 Reduction*
*These figures are approximate and based on performance of a traditional generator use of 10L of diesel an hour at £1.30/Litre
Get in touch to discuss your requirements





How Did You Hear About Us:
Would you like to Hire or Buy a Hussh Po:
Enquiry:
Want to talk to an expert about the best power supply for your setup?
Call us on:
03030 310409